Eureka 3D MSS Environment Plan has been ACCEPTED by NOPSEMA

NOPSEMA have now completed their assessment of the Environment Plan (“EP”) and is satisfied that the environmental impact and risk of the survey’s proposed operations are mitigated to as low as reasonably practicable, and remain acceptable, whilst adopting best practice methods, and meeting the requirements of Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023.

Environment Plan Preparation and Consultation Lifecycle

  • Timeline item 1 - complete

    Notice of preparation of an Environment Plan

    We are sharing information and inviting feedback on the activity, our consultation process and our risk management framework.

  • Timeline item 2 - complete

    Establishing context

    We will share a description of the environment, the legislative requirements that apply, our implementation strategy and a preliminary impact assessment.

  • Timeline item 3 - complete

    Environmental assessment

    We will share our detailed predictions of environmental impact and risk. Including any quantitative analysis we carry out.

  • Timeline item 4 - complete

    Environmental impact and risk treatment

    We will share our evaluations of environmental impact and risks and our treatment plans.

  • Timeline item 5 - complete

    Opportunity to raise objections or claims

    You can share your feedback at any time. At this time, we will share our draft submission and invite you to raise concerns and provide feedback to ensure your views have been taken into account before submission.

  • Timeline item 6 - complete

    Public Comment

    The Environment Plan was available for public comment between 22nd February to 22nd March 2024. It is still available to view on NOPSEMA website.

  • Timeline item 7 - complete

    Submission to NOPSEMA

    The Environment Plan approval document will be submitted to NOPSEMA for formal public comment and assessment.

  • Timeline item 8 - active

    Environment Plan Accepted - Ongoing consultation

    The Eureka 3D MSS EP has been accepted by NOPSEMA, we will continue consultation throughout the activity and respond to changing circumstances.